RCM Heat Map showing the 700m section transformation from high-resistance (red) to high-efficiency (green).
Productivity Snapshot
Shift Production Increase
+1,963 Tonnes
or +5.61 Payloads
Cycle Time Reduction
-12.8 Seconds
per cycle
Speed Improvement
+2.1 km/h
19.3 → 21.4 km/h
Technical Narrative
By utilizing real-time RCM data, site management identified and repaired 700m of the EX221 dig-floor in just two hours. This surgical maintenance improved the road score from 63.79% to 79.13%, directly impacting fuel consumption, tyre wear, and operator comfort.
The Fleet Math
For an 8-vehicle fleet of Liebherr T282s (350t payload) over a 12-hour shift, the cycle time reduction scales to nearly 2,000 additional tonnes moved without increasing fleet size.